Canal contract 2015

Canal contract 2015 from Serenato Construction

By: Serenato Construction  07-08-2015
Keywords: Building Contractors, Building & Construction, Bathroom Renovations

Repairs to the canal system during the months of April to July. These canals are used for irrigation by the local farming community. 2011 – 13000m² 2012 – 11000m² 2013 – 10500m² 2014 – 15500m² 2015 – in progress High-pressure cleaning of canal walls, sealing of joints at every 6m interval, re-plastering approximately 12mm with mortar and fibre mix of the canal system. Assigned tasks: Quality control, ordering of materials, wages & payment certificates, construction programme, as well as health, safety and environmental.